How to increase factory throughput by 31%?

Hofman-Słubice Sp. z o.o. is part of the Dutch holding company GS Hofman – a family-run company that’s unique due to its long-standing 160-year tradition. Hofman is a recognised European manufacturer of premium wooden windows. Thanks to modern machines, high-quality standards and values that have been passed down from generation to generation, the company makes competitive premium products. The company’s high quality is confirmed by the fact that it holds a Danish Royal Warrant of Appointment for its reliability in conducting business activities. The Polish plant currently employs over 100 people and operates continuously over three shifts. Every month, the Hofman factory produces approximately 5,000 windows, resulting in a turnover of PLN 25 million.

A problem and challenge – twice as many orders as production capacity

The production of custom-made timber windows has very high parameter variability. Hofman’s production is diverse and range from small, unpainted and simply constructed windows to the most-complex and sophisticated window systems delivered for large development projects. The variability exists because of the necessity to constantly adapt the production process and proper queueing of orders.

Due to the increasing demand for Hofman windows, the company was receiving more and more orders. The factory began having significant problems in timely production, despite having three shifts in a continuous 24/7 system.

“Along with the increase in sales, we exceeded the threshold of scale, after which the company loses efficiency. Excess orders made us gradually fall into chaos. At a critical moment, we were overloaded with orders by 100% in relation to production capacity. We had to carry out an organisational change to be able to execute orders more quickly and operate more efficiently,” said Przemysław Wojdyło, co-owner and vice-chairman of the Hofman-Słubice Management Board.

The excess orders caused a number of complications and problems, some of which became strategically important. It was difficult for the company to process orders on time, and the lead time exceeded 60 days. Delays caused customer dissatisfaction and frustration in the sales department, but they were also a factor that reduced the company’s competitiveness. Contracting orders in excess of production capacity led to a deterioration in quality. There were more and more mistakes in the process. The company was focused on the implementation of orders and lost the possibility of further development. All this had a negative impact on the team, resulting in exhaustion, loss of motivation, decreased productivity, the need to work overtime, etc.

QRM as the optimal solution

The Management Board learned about the QRM method from their business partner, who was implementing it with the help of a consulting company – 4Results. From the very outset, the Hofman Management Board was convinced that this was a method that could help reorganise the system sufficiently to extract the full potential from available resources.

How did Hofman release its full potential?

The implementation of QRM was meant to modify the company’s management system at the level of the organisational structure, processes and HR. The first stage of the project was analysis of the situation at the company, which showed the possibility of separating out interdisciplinary cells (Q-Cells) focused on shortening the order processing times.

At the level of the organisational structure, the necessary changes included a departure from the hierarchical model to improve cooperation and communication between specialist departments. “Eventually, three teams were created in the company. The first one covered office processes, where we prepare complete documentation for the production hall. The second team covered processes implemented in the production area. The third had functions supporting the organisation of work and communication between two cells”, said Przemysław Wojdyło.

“The selection of Q-Cell leaders from among employees brought significant benefits. It allowed some responsibility to be transferred to lower levels. This stimulated employee motivation and engagement. Leaders perform well as middle management, which means that the Management Board can move away from solving ad hoc problems, thus gaining a lot of time for strategic activities. In addition, the creation of cells managed by people from their own teams integrated the employees further. This had a very positive effect on the atmosphere at work”, said Przemysław Wojdyło co-owner and vice-chairman of the Hofman-Słubice Management Board.

The Q-Cells created have been equipped with tools to optimise work:

  • Methods of measuring MCT (Manufacturing Critical-Path Time), which is the time taken to process orders – from order placement to delivery of the finished product – were implemented.
  • A number of tools for process visualisation have been introduced, including resource availability (capacity), orders placed, daily work plan, order flow in the factory, etc.
  • Visualisation of the functioning of the office has been implemented, thanks to which it’s now possible to check precisely what tasks are carried out by the team and how much time they take.

An important element of the QRM project was working with people. First of all, competences in machine maintenance were improved so that more employees are able to independently solve most typical problems related to downtimes. The creation of Q-Cells enabled an analysis of the competences required for specific positions. As a result, a competence matrix was created; this became a tool supporting the remuneration system, and at the same time allowed teams to plan their own development.

Another important element of the QRM project was planning optimisation. The analyses quickly revealed production bottlenecks. One of these was the planning of deliveries and coordinating them with the production of finished products. As a result, the planning principle was implemented only up to a level of 80% of bottlenecks, so as not to slow down the entire process. In addition, improved planning translated into High Level Material Requirement Planning. Currently, employees are able to predict order fluctuations with greater accuracy.

 

Hard results

The project started in June 2017, and changes were noticeable already in November.

  • Despite the increase in the scale of operations, the company is currently planning to operate at only 80% of its production capacity. Employees have time to creatively solve ad hoc problems.
  • The order processing time has been decreased from over 60 days to less than 30 days. MCT in the production hall has been reduced by over 50% (with potential for further reduction), while in office processes it’s been decreased by as much as 70%.
  • Almost 100% of deliveries are currently completed on time or by a strictly defined, predictable time.
  • The company’s quality-control department was no longer necessary. By reorganising the structure and transferring responsibility to teams, all employees are quality controllers and take on responsibility for this.
  • Deliveries are on time and complete. We managed to get MCT from 60 days down to under 30 days.
  • The company has all the important indicators defining its condition, productivity and efficiency measured. It measures OEE and MCT on an ongoing basis both in the production hall and in the office, which is responsible for the administration and preparation of orders for production.
  • The company has reduced operating costs.
  • The company’s Management Board now has tools that clearly inform exactly what’s happening in the company, what the workflow looks like, and how much time is needed for individual tasks.
  • The company has improved relations with suppliers – it now knows in advance exactly which and how many materials it needs. It can also predict peak order levels. Thanks to this, the company has managed to reduce stocks and maintain delivery prices despite the overall increase in market prices.
  • The company has an integrated, close-knit team. Despite operating on a difficult labour market, there are no problems with maintaining competences and attracting new employees. Thanks to the good atmosphere, people recommend their friends to work at the company.
  • The company now has a competence-development model for all employees. A remuneration system linked to results has also been implemented.

„In the window industry, lead time is critical for customers. Deliveries must be coordinated with the end stage of the façade or dismantling of scaffolds. Previously, Hofman’s clients complained that deliveries were not at the right time. After the implementation of QRM, the company has full control over deadlines. If it wasn’t for weather conditions or unpredictable changes by customers, which disrupt MCT measurement, Hofman would achieve 100% on-time delivery.” Przemysław Wojdyło, co-owner and vice-chariman of the Hofman-Słubice Management Board.

“Thanks to QRM, we’re growing and enjoying a good reputation on the market. We guarantee fast delivery and good quality”, said Przemysław Wojdyło.